Published 3/24/2023 8:59:16 AM

Beginning Monday, September 18th, 2023, NE 38th Street north of NE 46th Avenue (Broadway) will be opened, NE 38th Street south of NE 46th Avenue (Broadway) will be closed & E 46th Street at NE 46th Avenue (Broadway) will be opened.

Beginning Monday, June 26th, 2023 NE 46th Street south of NE 46th Avenue (Broadway) will be closed.

Beginning Tuesday, June 13, 2023 NE 38 Street south of NE 46 Avenue (Broadway) will be closed.

Starting Monday, May 15th, Broadway/NE 46 Avenue west bound traffic will be shifted from the north to the south side of the road between Four Mile Creek & Hubbell Ave. & the NE 38th St. access to Broadway will be closed. Detours will be posted.

Starting Monday, April 24th, Broadway/NE 46 Avenue from NE 29 Street to Hubbell Avenue will be reduced to one lane. East bound traffic will be closed. West bound traffic only. Detours will be posted.

Work on roadway utilities at the intersection of E Broadway Ave and E 46th Street the first week of April 2023. E 46th Street will be closed north of Broadway Avenue during this work and a detour will be posted.

Please travel with caution in this area and obey all work zone signs and work zone speed limits.